Site Setup Sequence

SHORT TERM INSTALLATIONS

Site needs to be flat and reasonably level. For short term installations (1 to 12 months) the site can be leveled and stabilised with a CT base as below

PlatSetup1-300

PlatSetup2-300

Spreader assemblies are placed in rough position. These have tapered bushes to allow easy alignment of components. 2m In-fills positioned in the middle

PlatSetup3-300

PlatSetup4-300

The platform decks are then lowered onto the locators and ramps positioned at each end

PlatSetup5-300

PlatSetup6-300

The finished installation (approximately two(2) hours including running cables
One (1) scoreboard screen was used on this site showing Total Weights. Power is 12vdc supplied via battery with solar charging

LONG TERM / PERMANENT INSTALLATIONS

For permanent or long term installations it is recommended to use a concrete base. Here three concrete pads 3m x 4m were poured to level a sloping site.

18mSetup1-304

18mSetup2-304

Spreader assemblies are placed in rough position. These have tapered bushes to allow easy alignment of components.

18mSetup3-304

18mSetup4-304

Starting from the centre the Infil pieces are positioned

18mSetup5-304

18mSetup6-304

The platform decks are then lowered onto the locators and ramps positioned at each end

18mSetup7-304

18mSetup8-304

For this site concrete barriers were placed along sides of bridge. There are also optional heavy duty side guides available.
Three (3) scoreboard screens were used on this site showing Front, Rear and Total Weights. Power is 12vdc supplied via battery with solar charging